Dobrá časová osa, co se chystá u JWST v následujících dnech:
L+ 3.0 days - Deploy L and R forward unitized pallet structures
L+ 3.16 days - Deploy L and R aft unitized pallet structures
L+4.07d - Spacecraft-to-Optical Telescope Element launch release mechanism
L+4.1d - Spacecraft-to-ISIM Electronics Compartment launch release mechanism
L+ 4.2 days - Raise DTA (deployable telescope tower assembly)
L+ 4.48 days - Release CJAA (Cryocooler Jitter Attenuation Assy)
L+ 5.0 days - Release CCA (Cooler Compressor Assy)
L+ 5.05 days - Deploy solar trim tab (Aft Momentum Flap) on right(?) panel
L+ 5.1 days - Release sunshade restraints
L+5.17 days - Retract sunshade central covers
https://planet4589.org/space/misc/webb/time.html